✉ miguel@schedulers.cl 📞 +56 9 6221 5582
Excel · Digital download

Labor rates for construction and industrial installation

550+ labor rates to turn work quantities into job hours (man-hours) and durations, without starting from a blank sheet. Metric and imperial units, with adjustable PF and working hours.

Secure checkout by Hotmart. The total may vary with taxes and your local currency.

Cover of the Labor Rates Excel workbook for construction and industrial installation
Same trench, same crew

25 days or 57?

Hand-excavating 1,000 m³ (1,308 yd³) of trench up to 2 m (6.6 ft) deep, no hauling, with 10 workers, 8 effective hours and PF = 1. Only the ground changes.

25 days
Soft ground · 2.00 JH/m³ (1.53 JH/yd³)
57 days
Hard ground · 4.57 JH/m³ (3.50 JH/yd³)
100 days
Very hard ground · 8.00 JH/m³ (6.12 JH/yd³)
71 days
Hard ground with PF = 1.25

The math: 1,000 m³ × 4.57 JH/m³ = 4,570 JH. Divided by 10 workers × 8 hours, that is about 57 working days.

Free sample

See what you get before you buy

15 of the 550+ rates in the workbook, at PF = 1 and 8 effective hours per worker-day.

Work itemDaily outputRate
Residential civil works
Trench excavation 0-2 m, soft ground, no haulingTrench excavation 0-6.6 ft, soft ground, no hauling4.00 m³/WD5.23 yd³/WD2.00 JH/m³1.53 JH/yd³
Concrete mixing in a small drum mixer2.00 m³/WD2.62 yd³/WD4.00 JH/m³3.06 JH/yd³
Concrete placing in slabs, by wheelbarrow2.00 m³/WD2.62 yd³/WD4.00 JH/m³3.06 JH/yd³
Reinforcing steel A-44/A-56, bars 16-22 mmReinforcing steel A-44/A-56, bars 0.63-0.87 in100.00 kg/WD220.46 lb/WD0.080 JH/kg0.0363 JH/lb
Hand-molded brick or block walls, 15-20 cm thickHand-molded brick or block walls, 5.9-7.9 in thick5.50 m²/WD59.20 ft²/WD1.45 JH/m²0.135 JH/ft²
Industrial civil works
Formwork erecting and stripping, foundations3.50 m²/WD37.67 ft²/WD2.29 JH/m²0.212 JH/ft²
Concrete placing, volume over 2 m³Concrete placing, volume over 2.6 yd³2.67 m³/WD3.49 yd³/WD3.00 JH/m³2.29 JH/yd³
Structural steel and mechanical
Heavy steel erection180.00 kg/WD396.83 lb/WD44.44 JH/t40.32 JH/short ton
Medium equipment under 3,500 kg, one pieceMedium equipment under 7,716 lb, one piece95.00 kg/WD209.44 lb/WD84.21 JH/t76.39 JH/short ton
Piping and insulation
Butt-welded pipe, mining plants, average (6" dia., carbon steel)24.00 kg/WD52.91 lb/WD333.33 JH/t302.39 JH/short ton
Flanged valve installation, 4"1.00 ea/WD1.00 ea/WD8.00 JH/ea8.00 JH/ea
Pipe insulation, 2" dia., 1" thick6.00 m/WD19.69 ft/WD1.33 JH/m0.406 JH/ft
Electrical and instrumentation
Electrical cable tray, 12" wide1.00 m/WD3.28 ft/WD8.00 JH/m2.44 JH/ft
600 V cable, 1 conductor #16-10 AWG, pull and terminate100.00 m/WD328.08 ft/WD0.080 JH/m0.0244 JH/ft
Level transmitter installation0.667 ea/WD0.667 ea/WD12.00 JH/ea12.00 JH/ea

WD = worker-day. JH = job hours (man-hours). Average reference values: adjust them to the conditions of each project.

What's included

From excavation to instrumentation

Organized by trade in a single workbook, for estimators, planners, project controls, contractors, construction managers, inspectors and students.

  • Earthworks: by hand and by machine
  • Concrete: formwork, reinforcing steel and embedded items
  • Residential work: masonry, finishes, plumbing
  • Structural steel and platework: fabrication and erection
  • Mechanical installation: by industry and equipment type
  • Piping and welding: pipe, valves and joints
  • Electrical: lines, substations, raceways and cable
  • Instrumentation: raceways and instruments
  • Painting and coatings: blasting, painting and cladding
  • Insulation and refractories: pipe, equipment and tanks
How it works

Adjust it to your project in three steps

We use it to estimate job hours. Percentage allowances, equipment-hours and physical ratios are fixed values.

Enter your PF

JH per unit and daily output recalculate on both unit sheets.

Enter your working hours

Your effective hours recalculate the daily output.

Apply your quantities

Quantity × JH per unit gives your JH. Divide by crew size and hours to get the days.

FAQ

Before you buy

What do I get?

An editable Excel workbook (.xlsx) in English with two linked sheets, metric and imperial (US). Hotmart processes the payment and emails you the download access once it is confirmed.

What does JH mean?

JH = job hours: the hours worked by one person, also known as man-hours or labor hours.

What is PF?

The Performance Factor is JH spent divided by JH earned. Above 1 means more JH per unit; below 1, fewer.

Do working hours change the JH per unit?

No. Working hours change the daily output and therefore the duration. JH per unit change with the PF.

Are the imperial values rounded?

No. They are exact conversions of the metric rates, calculated in the workbook. Sizes in descriptions are rounded equivalents.

Where do the rates come from?

They are reference values from a technical labor-rates manual for construction and industrial installation, which we use to estimate job hours. They are averages for normal conditions: adjust them with the PF.

Does it build a full estimate?

No. It gives daily output and JH per unit. With your quantities, crew size and labor rates you get total JH, duration and cost.

Can I ask for a refund?

You can request one on Hotmart within 7 days. Under its Terms of Purchase, a request may be declined if the file was already downloaded, without prejudice to your rights under applicable law. That is why we show a sample before you buy. If you have a problem with the file, write to us and we will fix it.

Start your next bid with numbers you can build on.

550+ labor rates in Excel, metric and imperial, delivered once payment is confirmed.

Buy for USD 19.99 →